Question: CASE STUDY 1: JWD CONSULTING'S PROJECT MANAGEMENT INTRANET SITE PROJECT (PREDICTIVE APPROACH) The following fictitious case provides an example of the elements involved in managing a project from start to finish. This example also uses Microsoft Project to demonstrate how project management software can assist in several aspects of managing a project.

student submitted image, transcription available below

Instructions:

  • Write in your own words Develop a business case for an IT project .

Answer: 1.0 Introduction/Background JWD Consulting, a leading provider of project management consult...

answer image blur

Not the question you’re looking for?

Post any question and get expert help quickly.

  • High School
  • You don't have any recent items yet.
  • You don't have any courses yet.
  • You don't have any books yet.
  • You don't have any Studylists yet.
  • Information

JWD Consulting Case Study

It project management (stid3074), universiti utara malaysia, recommended for you, students also viewed.

  • Sejarah Penubuhan UMNO
  • Latar Belakang Mahkamah Syariah
  • Kes Hamzah bin Zainuddin v Noraini bte Abdul Rashid, [2008 ] 2 SHLR 79
  • 1076-irsyad-2019 - WORK
  • 36252 116588 2 PB - WORK

Related documents

  • Algoritma dan ralat coding
  • Charter - assignment
  • Exam 1 March 2018 2019, questions and answers
  • Configure automatic failover and read write splitting - RDS Postgre SQL Database Alibaba Cloud Documentation Center
  • Airline Reservation System
  • 8425 - Help for us

Preview text

Jwd consulting’s business case.

1 Introduction/Background

JWD Consulting’s core business goal is to provide world-class project management consulting services to various organizations. The CEO, Joe Fleming, believes the firm can streamline operations and increase business by providing information related to project management on its intranet site, making some information and services accessible to current and potential clients.

2 Business Objective

JWD Consulting’s strategic goals include continuing growth and profitability. The Project Management Intranet Site Project will support these goals by increasing visibility of the firm s expertise to current and potential clients by allowing client and public access to some sections of the intranet. It will also improve profitability by reducing internal costs by providing standard tools, techniques, templates, and project management knowledge to all internal consultants. Since JWD Consulting focuses on identifying profitable projects and measuring their value after completion, this project must meet those criteria.

3 Current Situation and Problem/Opportunity Statement

JWD Consulting has a corporate Web site as well as an intranet. The firm currently uses the Web site for marketing information. The primary use of the intranet is for human resource information, such as where consultants enter their hours on various projects, change and view their benefits information, access an online directory and Web-based e-mail system, and so on. The firm also uses an enterprise-wide project management system to track all project information, focusing on the status of deliverables and meeting scope, time, and cost goals. There is an opportunity to provide a new section on the intranet dedicated to sharing consultants project management knowledge across the organization. JWD Consulting only hires experienced consultants and gives them freedom to manage projects as they see fit. However, as the business grows and projects become more complex, even experienced project managers are looking for suggestions on how to work more effectively.

4 Critical Assumption and Constraints

The proposed intranet site must be a valuable asset for JWD Consulting. Current consultants and clients must actively support the project, and it must pay for itself within one year by reducing internal operating costs and generating new business. The Project Management Office manager must lead the effort, and the project team must include participants from several parts of the company, as well as current client organizations. The new system must run on existing hardware and software, and it should require minimal technical support. It must be easily accessible by consultants and clients and be secure from unauthorized users.

5 Analysis of Options and Recommendation

There are three options for addressing this opportunity:

Do nothing. The business is doing well, and we can continue to operate without this new project.

Purchase access to specialized software to support this new capability with little in-house development.

Design and implement the new intranet capabilities in-house using mostly existing hardware and software.

Based on discussions with stakeholders, we believe that option 3 is the best option.

6 Preliminary Project Requirements

The main features of the project management intranet site include the following:

Access to several project management templates and tools. Users must be able to search for templates and tools, read instructions on using these templates and tools, and see examples of how to apply them to real projects. Users must also be able to submit new templates and tools, which should be first screened or edited by the Project Management Office.

Access to relevant project management articles. Many consultants and clients feel as though there is an information overload when they research project management information. They often waste time they should be spending with their clients. The new intranet should include access to several important articles on various project management topics, which are searchable by topic, and allow users to request the Project Management Office staff to find additional articles to meet their needs.

Links to other, up-to-date Web sites, with brief descriptions of the main features of the external site.

An Ask the Expert feature to help build relationships with current and future clients and share knowledge with internal consultants.

Appropriate security to make the entire intranet site accessible to internal consultants and certain sections accessible to others.

The ability to charge money for access to some information. Some of the information and features of the intranet site should prompt external users to pay for the information or service. Payment options should include a credit card option or similar online payment transactions. After the system verifies payment, the user should be able to access or download the desired information.

Other features suggested by users, if they add value to the business.

7 Budget Estimate and Financial Analysis

A preliminary estimate of costs for the entire project is $140,000. This estimate is based on the project manager working about 20 hours per week for six months and other internal staff working a total of about 60 hours per week for six months. The customer representatives would not be paid for their assistance. A staff project manager would earn $50 per hour. The hourly rate for the other project team members would be $70 per hour, since some hours normally billed to clients may be needed for this project. The initial cost estimate also includes $10,000 for purchasing software and services from suppliers. After the project is completed, maintenance costs of $40,000 are included for each year, primarily to update the information and coordinate the Ask the Expert feature and online articles. Projected benefits are based on a reduction in hours consultants spend researching project management information, appropriate tools and templates, and so on. Projected benefits are also based on a small increase in profits due to new business generated by this project. If each of more than 400 consultants saved just 40 hours each year (less than one hour per week) and could bill that time to other projects that generate a conservative estimate of $10 per hour in profits, then the projected benefit would be $160,000 per year. If the new intranet increased business by just 1

  • Multiple Choice

Course : It Project Management (STID3074)

University : universiti utara malaysia.

jwd consulting case study summary

  • More from: It Project Management STID3074 Universiti Utara Malaysia 57   Documents Go to course

IMAGES

  1. JWD Consulting Case Study

    jwd consulting case study summary

  2. JWD Consulting Case Study

    jwd consulting case study summary

  3. CASE STUDY 1: JWD CONSULTING'S PROJECT MANAGEMENT

    jwd consulting case study summary

  4. SOLUTION: Jwd consulting case study thomas johnson iii

    jwd consulting case study summary

  5. Solved 1. Study JWD Consulting project management intranet

    jwd consulting case study summary

  6. JWD Business Case

    jwd consulting case study summary